The initial project scope of work included a pre-cast concrete structure within a structure. This design concept is a carryover from the grain industry. Process Plus proposed shifting to the S.O.P. for the meat processing industry, which is to utilize a steel frame construction with cooler panel wall and roof.
The result was essentially one building instead of two. This designed allowed for a faster construction schedule. This project was Design-Build, at risk.
System Includes:
- Meat Dumping
- Meat Processing Upgrades
- Pallet Feed System
- Warehouse Upgrades
- Water Tower Study
- Fire Loop Relocation
- Air Compressor Addition
- Ingredient Bins
- Finished Product Material Handling
- Equipment & Piping Specifications
- Micro Motion Piping