This facility is designed to better accommodate the development of pharmaceutical products. Key project challenges included raising the roof of an existing structure approximately 15 feet to accommodate vertically integrated process systems and rerouting utility and communications systems.

In addition, existing structural systems had to be reinforced to accommodate the added loads. These challenges were accommodated with zero down time on surrounding production operations.

System Includes:

  • Utilities
  • Air Handling Unit
  • CIP
  • Compactor
  • Mill
  • Screener
  • In-Bin Binder
  • Tablet Press
  • Gown/Degown
  • Equipment Wash Room

Value Provided:

  • Process Plus provided a 3-D model and virtual walk-through of the project structure, piping and ductwork to coordinate installation requirements with contractors for a cGMP compliant installation
  • Assisted client in the building permit review and approval process.
  • Continued implementation and review of facility Master Plan
  • Process Plus was on-site, responsible for coordination, design resolution and design conformance